What are the charges for utility connection permits?

Electricity Connection Permit Charges

These are fees paid to the local electricity board or utility provider to process and approve industrial power connections.

  • Application and processing fees typically range from ₹10,000 to ₹50,000
  • Load sanction fees vary based on the applied capacity (e.g., ₹500 to ₹1,000 per kW)
  • Security deposit may be required based on connected load and tariff category

Water Supply Permit Charges

Permit charges for water include connection approvals and municipal development fees, if applicable.

  • Connection fees generally range from ₹25,000 to ₹75,000 for industrial plots
  • Additional charges may apply for water meters, tapping points, and deposits
  • Long-distance connections may require added infrastructure contribution

Sewer and Drainage Connection Permits

Municipal bodies may charge for connection approvals, inspection, and infrastructure usage.

  • Permit charges range from ₹15,000 to ₹50,000 depending on location and pipe size
  • Inspection fees and one-time infrastructure levies may also be applied
  • Environmental clearance (if applicable) adds further documentation and fees