Date of Completion of the Report
The last Environmental Site Assessment (ESA) or Environmental Impact Assessment (EIA) report was completed on:
- Date: 28th March 2023
- Submitted by: M/s EnviroTech Consultants Pvt Ltd (NABET-accredited agency)
- Commissioned by: M/s ABC Industrial Developers Ltd for proposed industrial development at Survey No. 142/3, Sriperumbudur Taluk, Tamil Nadu
This report was part of the statutory documentation required for obtaining Consent to Establish (CTE) from the State Pollution Control Board.
Reporting Period and Study Duration
The environmental data used in the report was collected over a three-month baseline monitoring period, covering:
- Monitoring Duration: December 2022 to February 2023
- Scope of Study: Air quality, surface and groundwater analysis, soil sampling, noise monitoring, ecological and socio-economic assessment within a 10 km radius
- Public Consultation Date: 10th February 2023, coordinated with the District Collector’s Office
All sampling and analysis followed Central Pollution Control Board (CPCB) protocols.
Submission and Review Timeline
- Draft Report Submitted: 5th March 2023 to the Tamil Nadu State Environment Impact Assessment Authority (TNSEIAA)
- Final Approval and Review Closure: 14th April 2023
- Compliance Certificate Issued: 30th April 2023 by the State Pollution Control Board
The project was subsequently cleared for non-polluting industrial operations, subject to implementation of the Environmental Management Plan (EMP).